Section 6.11 - Budget Planning Worksheet

DOC-REF: FRC-CHK-001

FedRAMP Budget Planning Checklist

Every line item you need to present to your CFO or board when requesting FedRAMP authorization budget. Organized by phase with Low, Moderate, and High impact level ranges.

Note / Usage

Copy these tables into a spreadsheet for your budget presentation. Select the column matching your target impact level and adjust ranges based on your specific environment and security posture.

Section A. Pre-Authorization

Phase 1 line items

Pre-Authorization Costs
Line ItemLowModerateHigh
Gap Analysis / Readiness Assessment$15k - $30k$30k - $80k$60k - $120k
Consultant Selection and Contracting$5k - $10k$5k - $15k$10k - $20k
3PAO Selection and Contracting$5k - $10k$5k - $15k$10k - $20k
FedRAMP-Compliant Environment Buildout$20k - $50k$40k - $120k$80k - $200k
Security Tooling Procurement$25k - $60k$65k - $200k$100k - $300k
Staff Training and Onboarding$5k - $10k$5k - $20k$10k - $30k

Section B. Authorization

Phase 2 line items

Authorization Phase Costs
Line ItemLowModerateHigh
SSP Development$40k - $80k$50k - $200k$100k - $350k
Policy and Procedure Documentation$20k - $40k$30k - $80k$50k - $120k
OSCAL Package Conversion / Development$15k - $30k$30k - $80k$50k - $120k
3PAO Initial Assessment$100k - $200k$350k - $650k$700k - $1.2M
Remediation Budget$30k - $80k$100k - $300k$200k - $500k
Remediation Contingency (10-20%)$30k - $50k$80k - $200k$200k - $500k
3PAO Retesting After Remediation$15k - $30k$30k - $60k$50k - $100k
Agency Review Support$5k - $15k$10k - $30k$20k - $50k
FedRAMP PMO Coordination$5k - $10k$5k - $15k$10k - $20k

Section C. Post-Authorization (Annual)

Phase 3 line items

Post-Authorization Annual Costs
Line ItemLowModerateHigh
Monthly Vulnerability Scanning (annual)$12k - $24k$24k - $60k$48k - $120k
Annual Penetration Testing (annual)$15k - $30k$25k - $60k$40k - $80k
3PAO Annual Subset Assessment (annual)$30k - $60k$80k - $150k$150k - $300k
POA&M Management (annual)$5k - $12k$15k - $40k$30k - $60k
Incident Response Readiness (annual)$5k - $10k$15k - $30k$25k - $50k
SSP and Documentation Updates (annual)$8k - $15k$20k - $40k$30k - $60k
Significant Change Requests (annual)$5k - $10k$10k - $30k$20k - $50k
Dedicated Compliance Staff (annual)$60k - $90k$120k - $180k$150k - $220k
Security Tooling Renewals (annual)$20k - $50k$50k - $150k$80k - $250k

Section D - Indicative Totals

Budget Summary (Authorization + Year 1)

FedRAMP Low

$350k - $600k

+ $60k-$120k/yr ongoing

FedRAMP Moderate

$800k - $2.2M

+ $150k-$350k/yr ongoing

FedRAMP High

$2.5M - $5M+

+ $300k-$600k/yr ongoing

Section E. Common Mistakes

Six budget pitfalls to avoid

Under-budgeting remediation

The 3PAO almost always finds more issues than your internal gap analysis. Budget 10-20% of your total authorization cost as remediation contingency. Organizations that skip this line item regularly exceed budget by $100k-$300k.

Forgetting ConMon in year 1

Year-one ConMon starts immediately after ATO. Monthly vulnerability scanning, POA&M management, and incident response readiness begin on day one. Budget ConMon costs from the authorization date, not from year two.

Not accounting for staff time

FedRAMP consumes significant internal engineering and compliance time. For a 50-person engineering team, expect 2-4 FTE equivalents diverted for 12-18 months. A real cost even if no new hires are made.

Ignoring tooling costs

SIEM licensing, vulnerability scanning, EDR, encryption key management, and log aggregation add $65k-$300k/year for Moderate impact. These are not optional. Required to meet FedRAMP control baselines.

Treating authorization as a one-time cost

FedRAMP is an ongoing financial commitment. ConMon costs are perpetual. A $1M Moderate authorization becomes $2.5M-$4M over five years. Present 5-year TCO to your CFO, not just authorization cost.

Not budgeting for boundary expansion

Adding services or regions to your authorization boundary after ATO triggers Significant Change Requests. Each major boundary expansion can cost $50k-$200k. Budget for at least one expansion in the first two years.